LUSAIL CP-07B

Project Overview

Client/Owner Qatari Diar Real Estate Investment Company
Master Developer Lusail Real Estate Development Company
Concept Designer Worley-Parsons
PMCM Parsons
Consultant Dorsch
Contract Type Lump Sum, D&B
Contract Duration 1,329 days (44.3 m)
Early Duration 1,094 days (36 m)
Land Area 420,000 m2
Total Built-up area 151,198 m2
Location Lusail City
 

Project Scope of Work

  1. D&B Tunnel along Road A1 (Two Levels)
  2. D&B Combined LRT Station Structural and Civil Works
  3. D&B Multi-Story Underground Car Park
  4. D&B Bridge at Junction No. 19
  5. D&B Six 11KV Substations:
    • 3 Substations recently relocated outside the limit of the Project
    • 3 Substations inside the Car Park
  6. Infrastructure Utilities (Integration of the remaining networks including Electrical, Mechanical, Sewage, Irrigation, Storm and Tunnel Drain Network)
  7. Construction of Landscape and Public Realm Features
  8. D&B Gas, District Cooling and Pneumatic Waste Collection will be designed by MARAFEQ and integrated by DAR
  9. Design and construction of Enabling Works (Shoring / Dewatering system) – Design will be done by specialist sub-contractor and reviewed by DAR